Project Timeline

Day 0 Wednesday
Day 1 Thursday
Day 2 Friday
Day 3 Saturday
Day 4 Monday
Day 5 Tuesday

Same-Day Quote!

Chris called → Barbara set a 10-minute call with Mariusz → we asked for photos → Chris sent ~10 photos in ~2 hours → we measured from satellite → we emailed a detailed quote ~3 hours later.

Quote Review Call

4:00 PM review call. Chris accepted the quote before any in-person visit.

Pre-Construction Walk-Through

We walked the property with Chris to confirm the plan, talk through protection for landscaping/holiday lights, agree on work hours, delivery locations, dumpster placement (if any), and how we'd communicate daily updates.

Work Begins

Start removal of OMNI and add proper framing/backer.

Project Continues

Fascia wrap and prep.

Wrap Up

Install 6" K-style gutters + 3×4 downspouts; final cleanup and QC.